MADEPPA ENGINEERS & CONTRACTORS

Class-I Contractor · P.W.D. & K.U.W.S. & D. Board · Kalaburagi
Careers
Today

Where things stand

Projects

Progress against BOQ

From site

Open problems

KUIDFC / KUWS&D Board

Chittapur Town — Missing Sewerage Line

DiameterMaterialTender (m)Design (m)Variance (m)
Design quantity for 200mm dropped 426 m below tender, 160mm and 250mm both went up — worth a note in the next measurement book entry.
Site engineer entry

Daily progress log

DateProjectPipelineExcav.LayingBackfillRoadLabourJCBProblem
JCB · vehicles

Machinery log

DateMachineOperatorHoursDiesel (L)CostWork done
Stock

Material ledger

MaterialReceivedConsumedStockUnit
Costs so far

Expenses by category

Rough margin below is (contract value × % of design quantity executed) minus expenses logged — a stand-in for real billing figures. Swap in actual RA bill / certified amounts once those are tracked.
Expense log
DateProjectCategoryDescriptionAmount
Machine servicing
MachineLast servicedInterval (days)Next due
Extension of time

Hindrance and EOT tracker

This flags anything overdue in red the moment you open the page. For an actual push notification or SMS ahead of a deadline, that needs a small backend job or calendar integration on top of this.
ProjectHindranceRaisedExpected byDays pendingStatus